Construction Progress Porta Nova: Screening and Chalking
Currently, we are working on the construction of a new greenhouse for Porta Nova in Waddinxeen. At the beginning of March, the entire roof was already fully glazed! The men of El Flaco Scherminstallaties are now busy with installing the screens. A hortizontal duo screen is placed in the greenhouse. The duo screen consists of two screens on a wire bed. One is for the radiation of light and the other is for the climate in the greenhouse. This installation of the screens will take around eight weeks to complete.
Furthermore, small wooden stakes have been put in place for the technical area and the roof of the greenhouse has been chalked. Inside, the first excavations works started and soon the digging of the basins will begin. The drone images give a good overview of the progress of the project.
A quick view from inside the greenhouse.
The greenhouse is being chalked.
Porta Nova from above.
For more information, pictures and video's about this project: click HERE.