An important milestone for our project Royals Peppers in Waddinxveen (NL) today. The first sighting work is a fact!
The greenhouse for growing peppers, which is being built by our construction partner Voorwinden Groep, will measure 5.9 hectares in total. The steel construction will be completed in week 43 according to current planning. A start is also made with glazing in that week. These activities then take around three weeks. The installation of the air mechanism starts a week earlier. Finally, the facades will start in the second week of November.
The first steel of the Royal Peppers greenhouse is visible.