Skip to main content
08 August 2017

Progress Royal Peppers: Glazing started

The entire lower part of Royal Peppers has been constructed in no time at all. In less than five weeks all trellies, gutters and columns have been placed, and the gables have been finished. The ridge has been put into its final position everywhere. The underground rain water discharge has been installed and is hidden from view. This is the time for the glazing crews to suddenly appear, itching to get starting. Last Friday it was time to start. Ever since construction started, progress has been closely monitored from above and from ground level, with man pictures and movies as a result. Almost every week the drone took a look in Waddinxveen to keep track of it all.

Week 27

Havecon Royal Peppers 020
This is where you will enter the greenhouse

A week after the first steel was erected, almost three quarters of the construction was already installed. At the entrance of the greenhouse the last rain water discharge tubes are being dug in.

Havecon Royal Peppers 027
The mist had barely cleared in this picture. The speed at which this project is being built is only properly comprehended when viewed from above. 


From above: Three quarters of the steel structure has already been constructed in just one week time

Week 28

The inner structure of the greenhouse is finished, and work has shifted to the four gables. Digging works for the basins are almost completed.

Havecon Royal Peppers 031
The first purlins at the side gable have been bolted into position. This is the back side of the greenhouse, at the east, where the center isle will be.


From above: the inner construction is finished, construction has shifted to the gables

Week 29

Havecon Royal Peppers 038
The head gables are nearly done, and the ridges have been installed

The gables are being finished. The head gables have been finished, leaving only the side gables.


From above: The head gables are almost finished. The ridges are in position.

Week 31

Havecon Royal Peppers 041
Glazing crews hard at work

Six glazing crews are working simultaneously to make sure the roof is closed in two weeks. After the roof is finished, the gables will be equipped with glass.


From above: Glazing has begun

Havecon-Royal-Peppers 001
Havecon-Royal-Peppers 002
Havecon-Royal-Peppers 003
Havecon-Royal-Peppers 004
Havecon-Royal-Peppers 005
Havecon-Royal-Peppers 006
Havecon-Royal-Peppers 007
Havecon-Royal-Peppers 008
Havecon-Royal-Peppers 009
Havecon-Royal-Peppers 010
Havecon-Royal-Peppers 011
Havecon-Royal-Peppers 012
Havecon-Royal-Peppers 013
Havecon-Royal-Peppers 014
Havecon-Royal-Peppers 015
Havecon-Royal-Peppers 016
Havecon-Royal-Peppers 017
Havecon-Royal-Peppers 018
Havecon-Royal-Peppers 019
Havecon-Royal-Peppers 020
Havecon-Royal-Peppers 021
Havecon-Royal-Peppers 022
Havecon-Royal-Peppers 023
Havecon-Royal-Peppers 024
Havecon-Royal-Peppers 025
Havecon-Royal-Peppers 026
Havecon-Royal-Peppers 027
Havecon-Royal-Peppers 028
Havecon-Royal-Peppers 029
Havecon-Royal-Peppers 030
Havecon-Royal-Peppers 031
Havecon-Royal-Peppers 032
Havecon-Royal-Peppers 033
Havecon-Royal-Peppers 034
Havecon-Royal-Peppers 035
Havecon-Royal-Peppers 036
Havecon-Royal-Peppers 037
Havecon-Royal-Peppers 038
Havecon-Royal-Peppers 039
Havecon-Royal-Peppers 040
Havecon-Royal-Peppers 041
Havecon-Royal-Peppers 042
Havecon-Royal-Peppers 043
Havecon-Royal-Peppers 044
Havecon-Royal-Peppers 045
Havecon-Royal-Peppers 046
Havecon-Royal-Peppers 047
Havecon-Royal-Peppers 048
Havecon-Royal-Peppers 049
Havecon-Royal-Peppers 050
Havecon-Royal-Peppers 051
Havecon-Royal-Peppers 052
Havecon-Royal-Peppers 053
Havecon-Royal-Peppers 054
Havecon-Royal-Peppers 055
Havecon-Royal-Peppers 056
Havecon-Royal-Peppers 057
Havecon-Royal-Peppers 058
Havecon-Royal-Peppers 059
Havecon-Royal-Peppers 060
Havecon-Royal-Peppers 061
Havecon-Royal-Peppers 062
Havecon-Royal-Peppers 063
Havecon-Royal-Peppers 064
Havecon-Royal-Peppers 065
Havecon-Royal-Peppers 066
Havecon-Royal-Peppers 067
Havecon-Royal-Peppers 068
Havecon-Royal-Peppers 069
Havecon-Royal-Peppers 070
Havecon-Royal-Peppers 071
Havecon-Royal-Peppers 072
Havecon-Royal-Peppers 073
Havecon-Royal-Peppers 074
Havecon-Royal-Peppers 075
Havecon-Royal-Peppers 076
Havecon-Royal-Peppers 077
Havecon-Royal-Peppers 078
Havecon-Royal-Peppers 079
Havecon-Royal-Peppers 080
Havecon-Royal-Peppers 081
Havecon-Royal-Peppers 082
Havecon-Royal-Peppers 083
Havecon-Royal-Peppers 084
Havecon-Royal-Peppers 085
Havecon-Royal-Peppers 086
Havecon-Royal-Peppers 087
Havecon-Royal-Peppers 088
Havecon-Royal-Peppers 089
Havecon-Royal-Peppers 090
Havecon-Royal-Peppers 091
Havecon-Royal-Peppers 092

Let's keep in touch.

Logo Havecon - Horticulture Projects

Address


Havecon Horticultural Projects
Lorentzstraat 8
2665 JH Bleiswijk, Netherlands
+31 (0)10 266 32 70