We start this project update with the Canadian project Redsun. An extra long update, because there is plenty of activity going on in finishing both the greenhouse and the service area.
In the meantime the second boiler is in operation and the pipes in the boiler room are being insulated. The last adjustments to the CO2 system are now being made and finalized. The climate computer has arrived and will be installed and connected to all systems.
In addition, the general cleaning has started. In the irrigation room, the Tebarex water specialist is removing the last dust particles from the equipment. The units are ready for their final commissioning. In the greenhouse the gutters and walkway are being cleaned. The last step before planting!
The electrical panels are completely connected to all equipment in the greenhouse. The electrician from Gryphon is finishing up the last connection and has started further wiring the climate computer.
Finally, the horizontal screen is ready and all limits have been set. The screening crew from Alweco and Westland are working on the last limits of the gable screen.